1.) Contract Item / Service: Contracts (Lots 1 and 2) for the Supply of 3No. 15MVA 330/132/33KV and 12No. 60MVA
132/33KV Power Transformers for use in Transmission Sub-Stations
Name of Company:
Lot 1: Messrs Crompton Greaves Limited
Lot 2: Messrs Transformers & Rectifiers Limited
Cost: N2,750,910,958.45
Date: 26th November, 2008
Duration: 12 Months
2.0 Contract for 31 Ecological Projects
2.1) Contract Item / Service: Gully Erosion Project at Ojodu-Abiodun, Ogun State
Name of Company: Messrs Ambico Sendirian(Nig) Ltd
Cost: N299,543,681.80
Date: November 26, 2008
2.2 Contract Item/Service: Isingwu Umuahia and Ugwegbe Ariam Erosion control works, Abia State
Name of Company: Messrs Umez Engineering Construction Company Ltd
Cost: N281,182,983.80
Date: November 26, 2008
2.3 Contract Item/Service Procurement & installation of One Unit 400KG/HR Rotary Klin Medical Waste Incinerator and Ancillary Works at ABU Teaching Hospital, Zaria
Name of Company: Messrs Dinat Ventures Ltd.
Cost: N83,738,500.00
Date: November 26, 2008
2.4 Contract Item/Service: Construction of Drainages & Erosion control structures at Otuo, Owan East LGA, Edo State
Name of Company: Messrs Adiand Project (Nig.) Ltd
Cost: N182,531,874.30
Date: November 26 ,2008
2.5 Contract Item/ Service: Erosion and Flood control project in Abaji own FCT
Name of Company: Messrs Plovdiv (Nig.) Ltd
Cost: N102,684,061.50
Date: November 26, 2008
2.6 Contract Item/ Service: Herwa-Gana Erosion & Flood control works, Gombe Town, Gombe State
Name of Company: Messrs ZEF (Nig.) Ltd
Cost: N205.494,240.30
Date: November 26, 2008
2.7 Contract Service/Item: Flood and Erosion Control works at Amuzi Ahiara, Ahiazu Mbaise LGA, Imo State
Name of Company: Messrs Booreman Engineering Company Ltd.
Cost: N230,241,550.24
Date: November 26, 2008
2.8 Contract/Service Item: Flood & Erosion control project at Ikot Obio Ata, Nkwot, Ikono LGA, Akwa Ibom State
Name of Company: Messrs Bukham Eng. & Contr. Co. Nig. Ltd.
Cost: N299,290,195.85
Date: November 26, 2008
2.9 Contract/Service Item: Flood & Erosion Control Project at Afi Army Barracks, Edor, Ikom LGA, Cross River State
Name of Company: Messrs. Anbeez Services Ltd
Cost: N190,508,096.63
Date: November 26, 2008
2.10 Contract/Service Item: Zango Kataaf soil Erosion control roject, Kaduna State
Name of Company: Messrs Dan Mac Ventures Ltd.
Cost: N156,776,051.25
Date: November 26, 2008
2.11 Contract/Service Item: Flood & Erosion control project at Gashua, Bade LGA, Yobe State
Name of Company: Messrs Sim Investment Ltd.
Cost: N228,985,987.72
Date: November 26, 2008
2.12 Contract/Service Item: Procurement and Installation of One Unit 400KG/HR/Rotary Klin Medical Waste Incinerator and Ancillary Works at the Federal Medical Centre Azare, Bauchi State
Name of Company: Messrs Pericom (Nig.) Ltd.
Cost: N60,813,983.00
Date: November 26, 2008
2.13 Contract/Service Item: GRA Polo Ground Erosion control, Maiduguri, Borno State
Name of Company: Messrs Excavator International Ltd.
Cost: N176,981,596.31
Date: November 26, 2008
2.14 Contract/Service Item: Gully Erosion Project at Umunekwu-Ago, Isiukwuato LGA, Abia State
Name of Company: Messrs Safaar International Ltd.
Cost: N279,211,297.70
Cost: N176,981,596.31
Date: November 26, 2008
2.15 Contract/Service Item: Flood & Erosion control project at Gerei Bridge, Gerei LGA, Adamawa State
Name of Company: Messrs AGG & P Int’l Serv. Ltd.
Cost: N130,850,000.00
Date: November 26, 2008
2.16 Contract/Service Item: Isampou shoreline protection project, Aleibiri-isampou Ekeremor LGA, Bayelsa State
Name of Company: Messrs Oniansons Ltd.
Cost: N164,815,481.25
Date: November 26, 2008
2.17 Contract/Service Item: Flood control project at Abaganaram/Ngomari, Borno State
Name of Company: Messrs Feigen(Nig.) Ltd.
Cost: N166,369,951.13
Date: November 26, 2008
2.18 Contract/Service Item: Flood and Erosion control project Makera/Kakuri Industrial Area, Kaduna State
Name of Company: Messrs Belton Concept Ltd.
Cost: N85,115,013.70
Date: November 26, 2008
2.19 Contract/Service Item: Flood and Erosion control project at Ibokun, Osun State
Name of Company: Messrs De-Tither Int’l Ltd.
Cost: N135,090,372.38
Date: November 26, 2008
2.20 Contract/Service Item: Erosion & Flood control works at Ikot Enobong, Calabar Municipality, Cross River State
Name of Company: Messrs C.I.N Ltd
Cost: N169,356,876.50
Date: November 26, 2008
2.21 Contract/Service Item: Construction of gully Erosion control measures at Nkwere Umudim, Oji River LGA, Enugu State.
Name of Company: Messrs Anbeez Services Ltd.
Cost: N148,843,189.13
Date: November 26, 2008
2.22 Contract/Service Item: Flood & Erosion control works at Sharada GRA (Phase I), Kano State
Name of Company: Messrs AMG Worldwide Ltd.
Cost: N90,774,750.00
Date: November 26, 2008
2.23 Contract/Service Item: Soil Erosion & Flood control project at Katsina, Katsina State
Name of Company: Messrs Gusau & Rara Construction Company Ltd.
Cost: N189,192,956.30
Date: November 26, 2008
2.24 Contract/Service Item: Soil erosion & Flood control Works at Zuru, Zuru LGA, Kebbi State
Name of Company: Messrs Zoha Ent.(Nig.) Ltd.
Cost: N119,587,371.75
Date: November 26, 2008
2.25 Contract/Service Item: Idah-Ejule road erosion control project, Kogi State
Name of Company: Messrs Baron Properties & Dev. (Nig.) Ltd.
Cost: N134,557,153.50
Date: November 26, 2008
2.26 Contract/Service Item: Purchase & Supply of 3No. MBLK Mercedes Benz Sewage tankers to the University of
Maiduguri Teaching hospital & federal Medical Centres in Gombe and Yola
Name of Company: Messrs Sankey ltd.
Cost: N61,403,340.75
Date: November 26, 2008
2.27 Contract/Service Item: Erosion & Flood control project Phase I, at Nataco Area/Umomi, Kogi State
Name of Company: Messrs Fraggi (Nig.) Ltd.
Cost: N147,196,365.41
Date: November 26, 2008
2.28 Contract/Service Item: Erosion & Flood control works at Esun, Olope, Ugbesi, Aiyetoro and Odo-Ora, Ekiti State
Name of Company: Messrs Oweni(Nig.) Ltd.
Cost: N133,510,921.90
Date: November 26, 2008
2.29 Contract/Service Item: Flood & erosion control project at Queen ede College Road, Benin City, edo State
Name of Company: Messrs Oweni(Nig.) Ltd.
Cost: N101,616,180.60
Date: November 26, 2008
2.30 Contract/Service Item: Construction of soil erosion and flood control works along Ugboju-Agatu in Benue State
Name of Company: Messrs Amitech Engineering Ltd.
Cost: N120,034,530.00
Date: November 26, 2008
2.31 Contract/Service Item: Erosion control works at Nawfijah, Orumba South, Anambra State
Name of Company: Messrs Tripod Resources Ltd.
Cost: N482,966,593.80
Date: November 26, 2008
3.) Contract/Service Item: Contract for consultancy Services for the Engineering Supervision of the Completion of the Kontagora (Auna) Dam and Irrigation project
Name of Company: Messrs Tahal Consultant Group/Water and Dams Services Company.
Cost: N71,706,572.56
Date: November 26, 2008
4.) Contract/Service Item: Award of Supervision contract for Middle Rima Valley Irrigation Project, Phase II, Sokoto State.
Name of Company: Messrs Afremedev Consultancy Services Limited
Cost: N109,876,758.20
Date: November 26, 2008
Duration: 60 Months
5.) Contract/Service Item: Implementation of Quaranteed Minimum Price and the 2008 Purchase of Assorted Food Commodities for the National Strategic Reserve
Company: -
Cost: (a) N7.79billion for 194,600 metric tons of Assorted food commodities
(b) N 970million as Commission to the LBAs for their services.
Date: November 26, 2008
6.) Contract/Service Item: Procurement of Life- Saving Items (Steel Helmets) for the Nigerian Army
Name of Company: Messrs Royalton (Nig.) Ltd.
Cost: N120,000,000.00
Date: November 26, 2008
Duration: 6 Weeks
7.) Contract/Service Item: Contract for the Procurement of Combat Boots for the Nigerian Army
Name of Company: Messrs Rajco International Limited
Cost: N57,750,000.00
Date: November 26, 2008
Duration: 5 Weeks
8.) Contract/Service Item: Procurement of Troops Carrying Vehicles for the Nigerian Army
Name of Company: Messr Nigerian Motors Industries Limited
Cost: N198,832,497.60
Date: November 26, 2008
Duration: 4 Weeks
9.) Contract/Service Item: Direct Procurement of 5 No. Otis Model Lifts for the Ministry of Finance, Phase I, Complex, Abuja
Name of Company: Messrs CFAO Technologies
Cost: N147,670,425.00
Date: November 26, 2008
Duration: 20 Weeks
10.) Contract/Service Item: Contracts for the construction Works at the University of Ilorin Teaching Hospital, Ilorin, Kwara State
Name of Company: (a) Messrs Ometra Construction Engineers Limited -
Duration: 34 Weeks
(b) Construction of the Administrative Building Phase I
Duration: 24 Weeks
(c ) Installation of 2No. Lift Double Cars
Duration: 18 Weeks
Cost: N317,845,838.63
Date: November 26, 2008
11.) Contract/Service Item: Contracts for the construction Works at the National Orthopaedic Hospital, Dala Kano State
Name of Company: Messrs Afdin Construction Limited
Cost: N72,768,444.00
Date: November 26, 2008
Duration: 16 Weeks
12.) Contract/Service Item: Contract for the construction of a 25 Meter Radio Telescope Antenna at the Center for Basic Space Science Permanent Site
Name of Company: Messrs Allteche Technology Limited
Cost: N276,000,000.00
Date: November 26, 2008
Duration: 20 Months
13.) Contract/Service Item: Construction of the Permanent Head Office Building at the Sheda Science and Technology Complex, Abuja
Name of Company: (a) Messrs Godab (Nigeria) Limited
Cost: N470,022,245.63
(b) Messrs Almog Engineering Limited
Cost: N147,136,914.80
Date: November 26, 2008
Duration: 36 Weeks
14.) Contract/Service Item: Contract for the Rehabilitation of Tin- Can Island Port(Quay and Quay Apron)
Name of Company: Messrs Johnak Engineering Limited
Cost: N2,600,000,000.00
Date: November 26, 2008
Duration: 24 Months