FEDERAL EXECUTIVE COUNCIL APPROVED CONTRACTS FOR DECEMBER 10, 2008
1.) Contract Item / Service: Contract for the supply and installation of 3no. 1,000KVA High Tension Generators at the Shehu Shagari Presidential Complex, Abuja
Name of Firm: Messrs GIT Engineering Limited(inclusive of VAT & Withholding Tax)
Cost: N187,997,771.25
Date: 10th December, 2008
Duration: 4 Weeks
2.) Contract Item / Service: Contract for the Supply of 1No. Fire Engine Truck to the Federal Secretariat, Phase 1, Abuja
Name of Firm: Messrs Cospam (Nigeria) Limited (inclusive of VAT & Withholding Tax)
Cost: N57,420, 000.00
Date: 10th December, 2008
Duration: -
3.) Contract Item / Service: Contract for the Provision of spare parts for Artillery Guns for the Nigerian Army
Name of Firm: Messrs TS-Y Limited
Cost: N475,000,000.00
Date: 10th December, 2008
Duration: 6 Weeks
4.) Request For The Use Of Internally Generated Revenue(IGR) Of Some Of The Tertiary Institutions Of The Federal Ministry Of Education To Execute Their Projects
4.1.) Institution: Federal University of Technology Minna
Project: Construction of SET Building(Phase I)
Contractor: Messrs Dekkit Construction Ltd
Project Cost: N354,013,590.56
Completion Period: 32 Weeks
4.2.) Institution: Waziri Umar Federal Polytechnic B/Kebbi
Project: Construction of Administrative Building (Lot A)
Contractor: Messrs Solamid (Nig) Ltd
Project Cost: N194,918,412.00
Completion Period: 24 Weeks
4.3.) Institution: Usman Dan Fodio University, Sokoto
Project: Construction of College of Health Sciences Complex(Phase I)
Contractor: Messrs Maidoya Construction Co. Ltd.
Project Cost: N153,935,297.25
Completion Period: 50 Weeks
4.4.) Institution: Usman Dan Fodio University, Sokoto
Project: Construction of Department of Civil Engineering(Phase II)
Contractor: Messrs ProDev(Nig) Limited
Project Cost: N164,714,501.00
Completion Period: 52 Weeks
4.5.) Institution: University of Maiduguri
Project: Construction of Seventy Room Female Hostel Block
Contractor: Messrs Castle Gate Int. Ltd.
Project Cost: N97,676,794.50
Completion Period: 20 Weeks
4.6.) Institution: University of Maiduguri
Project: Construction of AGROVET Extension (Phase III) of Fac. Of Veterinary Medicine
Contractor: Messrs Golfa Int. (Nig.) Limited
Project Cost: N82,706,579.55
Completion Period: 18 Weeks
4.7.) Institution: Micheal Okpara University of Agriculture Umudike
Project: Completion of the Auditorium Building (Phase I)
Contractor: Messrs Saar(Nig.) Limited
Project Cost: N104,463,852.60
Completion Period: 22 Weeks
4.8) Institution: Nnamdi Azikiwe University Awka
Project: Completion of the Students’ Hostel (Phase iV)
Contractor: Messrs Vivid Construction Limited
Project Cost: N228,775,229.38
Completion Period: 44 Weeks
4.9.) Institution: Federal University of Technology Owerri
Project: Construction of School of Post Graduate Building
Contractor: Messrs Bussdor (Nig.) Limited
Project Cost: N87,249,007.75
Completion Period: 24 Weeks
4.10) Institution: University of llorin
Project: Construction of Offices and Lecture Halls of COHS/BBS
Contractor: Messrs Boyes international Limited
Project Cost: N300,196,408.05
Completion Period: 42 Weeks
Project: Construction of Offices for the faculty of Business and Social Sciences
Contractor: Basg Engineers (Nig) Limited
Project Cost: N125,630,031.45
Completion Period: 20 Weeks
Project: Construction of Faculty of Law (Phase II)
Contractor: Three O’s (Nig) Limited
Project Cost: N64,451,016.00
Completion Period: 20 Weeks
Project: Construction of Professional suites for Faculty of Social Sciences Building (Phase I)
Contractor: IIIL Mm(Nig) Limited
Project Cost: N84,769,591.88
Completion Period: 40 Weeks
4.11.) Institution: University of Uyo
Project: Construction of Health Centre at the main Campus
Contractor: Messrs Pavilland Construction Company Limited
Project Cost: N130,705,152.00
Completion Period: 24 Weeks
4.12.) Institution: University of Uyo
Project: Construction of Central Admin Block (Phase I) at the main Campus
Contractor: Messrs Ebom Brothers Limited
Project Cost: N217,915,130.00
Completion Period: 50 Weeks
Contractor: Messrs Sosay (Nig) Limited
Project Cost: N183,054,895.00
Completion Period: 50 Weeks
4.13.) Institution: Akanu Ibiam Fed. Poly Unwana
Project: Construction of Medical Centre
Contractor: Messrs Elkson Global Limited
Project Cost: N71,665,140.50
Completion Period: 28 Weeks
4.14.) Institution: Federal Poly Kaura Namoda
Project: Construction of Architectural Department
Contractor: Messrs Isma General Ent. Ltd
Project Cost: N82,030,725.00
Completion Period: 28 Weeks
Project: Construiction of Admin Block
Contractor: Messrs. Sozeal(Nig.) Limited
Project Cost: N128,732,609.92
Completion Period: 28 Weeks
4.15.) Institution: University of Nigeria Nsukka
Project: Completion of Faculty of Med./Dentistry
Contractor: Messrs Nathan Xtopher Construction Limited
Project Cost: N631,802,524.50
Completion Period: 52 Weeks
4.16.) Institution: Federal Polytechnic, Nekede, Owerri
Project: Design and Production of the Polytechnic Master Plan
Contractor: Messrs Nestoti Consultants
Project Cost: N75,218,171.27
Completion Period: 24 Weeks
5.) Contract Item / Service: Contract for the Expansion Passenger Apron at the Port Harcourt International Airport, Port Harcourt, Rivers State
Name of Firm: Messrs Trident Technologies and Allied Services Limited
Cost: N506,020,058.78
Date: 10th December, 2008
Duration: 12 Months
6.) Contract Item / Service: Contract for the Upgrading of the Airfield Lighting System of Domestic Runway of the Murtala Muhammed International Airport to Category III
Name of Firm: Messrs PPC Limited
Cost: N960,551,510.81
Date: 10th December, 2008
Duration: 6 Months