Federal Executive Council - FEC Approved Contracts For December 16, 2009

Posted by Kelvin on Mon 08th Oct, 2012 - nigeriantenders.com






FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS FOR DECEMBER 16, 2009

1.  Contract Item/ Service:  Award of Contract for the Revised Estimated Consultancy Services & the Framework Designed to Complete Zobe Water Supply Project in Katsina State(Phase 1)

Name of Company:Messrs. Gauff Ingenieure/Ecological Consultants (Nig) Limited

Implementing Agency: Federal Ministry of Agriculture & Water Resources

Cost: From N123,266,673.60 To N299,267,869.05 & (N205,673,698.53 Plus Euro623,932.02) for the extension of the consultants services

Date:16/12/09

Duration: 2011

2.  Contract Item/ Service: Award of Contract for the Augmentation of the Northern Ishan Water Supply Project in Edo State

Name of Company:
Messrs. CGC (Nigeria) Limited

Implementing Agency: Federal Ministry of Agriculture & Water Resources

Cost: Revised Estimated Cost From N2,245,858,443.12 To N2,497,255,752.09

Date: 16/12/09

Duration:14 Weeks

3. Contract Item/ Service: Award of the Restructuring of the Project Cost and Provision of a Provisional Sum on the  Contract for the Engineering, Procurement and Construction of a Dual-Fired (LPFO/Natural Gas) 215MW (ISO) Power Plant at Kaduna

Name of Company:
Messrs. General Electric/Rockson Engineering

Implementing Agency:
Federal Ministry of Power

Cost: Revised Project Cost From €100,525,856.08 Plus N8,401,987,889.10 To €135,840,665.71  Plus N6,066,626,449.24 inclusive of a Provisional sum of N3,000,000,000

Date:
16/12/09

Duration:

4. Contract Item/ Service: Award of Contract for the Design, Manufacture and Supply of 3Nos 30/40MVA 132/33KV Mobile Substations and Associated Spare Parts

Name of Company: Messrs. Puawels N.V.

Implementing Agency: Federal Ministry of Power/ Transmission Company of Nigeria Plc

Cost: €5,348,393.69 Plus N110,643,653.63

Date: 16/12/09

Duration: 16 Months

5. Contract Item/ Service: Award of Contract for the Construction of the Second Runway at Nnamdi Azikiwe International Airport, Abuja

Name of Company: Messrs. Julius Berger (Nigeria) Plc

Implementing Agency: Federal Ministry of Aviation

Cost: N63,584,605,157.41

Date: 16/12/09

Duration: 24 Months

6. Contract Item/ Service: Award of Contract for the Review of the Consultancy Services in respect of Abuja Geographic Information Systems (AGIS) AGIS II

Name of Company: Messrs. Julius Berger (Nigeria) Plc

Implementing Agency:Ministry of Federal Capital Territory

Cost: Contract Sum From N1,208,573,999.32 To N2,089,322,513.13

Date: 16/12/09

Duration: 30 Months

7. Contract Item/ Service: Award of Contract for the Rehabilitation of the Railway Tracks and Signals Network – Western Line (Contract No.2) Jebba to Kano (Km 488-Km 1126)

Name of Company: Messrs. Costain West Africa Plc.

Implementing Agency: Ministry of Transport

Cost: N12,167,826,578.56

Date:16/12/09

Duration:10 Months

8. Contract Item/ Service: Award of the Augmentation of Contract No. 5099 for the Reconstruction of Vom-Manchok Road in Plateau State

Name of Company:
Messrs. P.W. (Nigeria) Limited

Implementing Agency: Federal Ministry of Works

Cost: Contract Sum From N3,768,947,003.46 To N3,992,792,810.61

Date: 16/12/09

Duration:18 Months


Industry

;