Federal Executive Council (FEC) Approved Contracts for August 25, 2010

Posted by Chinyere on Tue 09th Oct, 2012 - nigeriantenders.com






FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS FOR AUGUST 25, 2010

1) Item/Service:
Award of Contract for the Extension of the Consultancy Services on Quickwins 2009 Projects
Name of Company: Messrs. Etat Consulting Limited
Implementing Agency: OSSAP-MDGs
Cost: N222,463,955.49
Date: 25/08/10
Duration: July 2010 – March, 2011

2) Item/Service: Award of for Additional Reimbursable Expenses on the Consultancy Services for Quickwins 2008 Projects
Name of Company: Messrs. Etat Consulting Limited
Implementing Agency: OSSAP-MDGs
Cost: N76,985,426.44
Date: 25/08/10
Duration: FY 2009

3) Item/Service: Award of Contract for the Augmentation of Project Cost of Additional Essential Work for the Completion of Power Supply Improvement Project at the Murtala Mohammed International Airport
Name of Company: Messrs. MANTRAC (Nigeria) Limited
Implementing Agency: Federal Ministry of Aviation
Cost: N7,719,751,577.07 (From N1,058,692,081.00 To N6,661,059,496.07)
Date: 25/08/10
Duration: 24 Months

4) Item/Service: Award of the Contract for the Design, Supply, Installation and Implementation of the Unique Taxpayer Identification Number Infrastructure and Systems
Name of Company: Messrs. TELNET Consortium
Implementing Agency: Federal Ministry of Finance
Cost: USD22,594,923.14 Plus N40,593,000.00
Date: 25/08/10
Duration: 3 Years (2009-2011)

5) Item/Service: Award Contract for the Claim for Additional Construction of 2x30/40MVA Sub-stations at Dutse and Azare
Name of Company: Messrs. ABB Limited
Implementing Agency: Federal Ministry of Power
Cost: USD12,500,000.00 Plus N97,739,058.00
Date: 25/08/10
Duration:

6) Item/Service: Award of Contract for the Supply of 42No. Transmission line Surveillance Vehicles for the Transmission Company of Nigeria Plc.
Name of Company: Messrs. Coscharis Motors Limited (42No. Units of Land Rovers 100XS 4WD)
Implementing Agency: Federal Ministry of Power
Cost: N336,928,899.50
Date: 25/08/10
Duration: 1 Week

7) Item/Service:
Award of the Revision of Contract Sum for the Delta II & III Power Station First HOT Gas Path Inspection and Manpower Services
Name of Company: Messrs. Marubeni Engineering (West Africa) Ltd.
Implementing Agency: Federal Ministry of Power
Cost: Revised the total Contract Sum From USD12,834,000.00 To USD13,692,000.00
Date: 25/08/10
Duration: 4 Months

8) Item/Service: Award of the Augmentation of Contract No. 5997 for the Rehabilitation of the outstanding 45Km of the Katsina-Daura Section as Addendum to the Kano-Kazaure-Daura-Mai’Adua and Katsina-Daura-Zango Road in Katsina State
Name of Company: Messrs. Triacta (Nigeria) Limited
Implementing Agency: Federal Ministry of Works
Cost: Revised Contract Sum From N2,319,910,477.50 To N4,727,405,874.35
Date: 25/08/10
Duration: 18 Months

9) Award of 9 contracts for the construction and rehabilitation of federal roads and bridges nationwide in favour of the following contractors with completion periods as shown below

i) Project: Noth- Central Zone Rehabilitation of Lafia –Obi-Awe-Tunga Road in Nasarawa State C/No. 6065
Recommended Contractor: Messrs. Triacta (Nig.) Ltd.
Recommended Contract Sum (N): 7,935,044,748.75
Completion Period: 24 Months
Amended 2010 Appropriation (N): 4,200,000,000

ii) Project: Rehabilitation of Jebba Bridge in Kwara State C/No. 6066
Recommended Contractor: Messrs. Borini Prono
Recommended Contract Sum (N): 2,059,422,019.20
Completion Period: 9 Months
Amended 2010 Appropriation (N): 1,350,000,000

iii) Project: North -East Zone
Rehabilitation of Potiscum-Udubo-Gamawa-Katagum-Gamayin Road Section II & III in Yobe and Bauchi States C/No. 6067
Recommended Contractor: Messrs. Mothercat Ltd.
Recommended Contract Sum (N): 4,636,709,720.11
Completion Period: 30 Months
Amended 2010 Appropriation (N): 2,200,000,000

iv) Project: Rehabilitation and Asphalt Overlay of Bauchi-Dass-Tafawa Balewa Road in Bauchi State C/No. 6068
Recommended Contractor: Messrs Triacta (Nig) Ltd.
Recommended Contract Sum (N): 4,584,975,576.72
Completion Period: 24 Months
Amended 2010 Appropriation (N): 2,250,000,000

v) Project: Rehabilitation of Maiduguri-Dikwa-Gamboru-Road Section II: Dikwa-Gamboru in Borno State C/No. 6069
Recommended Contractor: Messrs. CGC Nig. Ltd.
Recommended Contract Sum (N): 16,683,596,891.08
Completion Period: 24 Months
Amended 2010 Appropriation (N): 4,500,000,000

vi) Project: Rehabilitation and Asphalt overlay of Yana-Shira-Azare Road in Bauchi State C/No. 6070
Recommended Contractor: Messrs. Mothercat Ltd.
Recommended Contract Sum (N): 2,115,147,946.63
Completion Period: 9 Months
Amended 2010 Appropriation (N): 1,125,000,000

vii) Project: Construction of Damasak-Dutse (Nigeria) Diffa (Niger Republic) Road in Borno State C/No. 6071
Recommended Contractor: Messrs. CGC Nig. Ltd.
Recommended Contract Sum (N): 9,880,524,657.27
Completion Period: 24 Months
Amended 2010 Appropriation (N): 3,500,000,000

viii) Project: North - West Zone
Rehabilitation of Hadejia-Nguru Road Phase II: Kirikasamma-Nguru in Jigawa State C/No. 6072
Recommended Contractor: Messrs. Mothercat Ltd.
Recommended Contract Sum (N): 7,953,487,029.18
Completion Period: 32 Months
Amended 2010 Appropriation (N): 3,150,000,000

xi) Project: South- East Zone
Rehabilitation of Oji-Achi Obeagu-Mmaku-Awgu-Ndeaboh-Mpu-Okpanku in Enugu and Ebonyi States C/No. 6073
Recommended Contractor: Messrs. Setraco Nig. Ltd.
Recommended Contract Sum (N): 9,506,577,592.55
Completion Period: 24 Months
Amended 2010 Appropriation (N): 2,000,000,000
Total: 65,555,485,981.49, 24,275,000,000