FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS FOR MAY 18, 2011
1.) AWARD OF CONTRACTS FOR 10 INFRASTRUCTURAL DEVELOPMENT PROJECTS IN 9 STATES OF THE NIGER DELTA REGION (NDDC)
i.) Project Description: Construction of Umukukoir-Omumauzor-Ariara Junction, Abia State
Name of Contractor: Messrs. Burnsville Integrated Services Limited
Reviewed Project Cost (N): 733,085,543.42
Date: 18th May, 2011
Duration: 72 Weeks
ii.) Project Description: Construction of Ntala Oloko Nchara Road, Abia State
Name of Contractor: Messrs. E & A Nig. Ltd
Reviewed Project Cost (N): 1,555,797,965.76
Date: 18th May, 2011
Duration: 62 Weeks
iii.) Project Description: Construction of Internal Roads in Eastern Obolo Lot 1, Akwa Ibom State
Name of Contractor: Messrs. Konaliz Investment Limited
Reviewed Project Cost (N): 2,858,563,499.75
Date: 18th May, 2011
Duration: 16 Months
iv.) Project Description: Construction of Internal Roads in Eastern Obolo Obolo Lot 2, Akwa Ibom State
Name of Contractor: Messrs. Genco Construction Company Nigeria Limited
Reviewed Project Cost (N): 1,824,873,728.90
Date: 18th May, 2011
Duration: 104 Weeks
v.) Project Description: Shore Protection at Otuabagi, Bayelsa State
Name of Contractor: Messrs. Inter Global Technologies Limited
Reviewed Project Cost (N): 1,459,572,415.17
Date: 18th May, 2011
Duration: 72 weeks
vi.) Project Description: Construction of Etono-Biakpan Asanga Road/Bridge, Cross River State
Name of Contractor: Messrs. Samnamie Nigeria Company Limited
Reviewed Project Cost (N): 6,153,891568.00
Date: 18th May, 2011
Duration: 52 weeks
vii.) Project Description: Construction of Ativwor-Idjeoaka Adjawini Road, Delta State
Name of Contractor: Messrs. Niger Construction Limited
Reviewed Project Cost (N): 2,329,542,017.63
Date: 18th May, 2011
Duration: 82 Weeks
viii.) Project Description: Construction of Owevwe Otokutu Agbarda Road, Delta State
Name of Contractor: Messrs. Solotus Nigeria Limited
Reviewed Project Cost (N): 1,657,774,323.67
Date: 18th May, 2011
Duration: 52 Weeks
ix.) Project Description: Construction of Oha Oviri Court Road, Edo State
Name of Contractor: Messrs. Hi-Tech Construction Limited
Reviewed Project Cost (N): 2,744,098,678.31
Date: 18th May, 2011
x.) Project Description: Construction of Agbarho Community Internal Roads, Delta State
Name of Contractor: Messrs. Sevana Rocks Limited
Reviewed Project Cost (N): 2,400,045,149.25
Date: 18th May, 2011
Duration: 82 Weeks
TOTAL : 23,717,244,889.86
2.) AWARD OF CONTRACTS FOR 3 LAND RECLAMATION AND EROSION CONTROL/SHORELINE PROJECTS IN THE NIGER DELTA REGION BY MINISTRY OF NIGER DELTA AFFAIRS
i.) Project Description: Land Reclamation/Erosion Control at Essien Town-Ekorinin Community, Cross River State
Name of Contractor: Messrs. A.G Vision Construction Nigeria Limited
Reviewed Project Cost (N): 1,948,302,432.28
Date: 18th May, 2011
Duration: 12 Months
ii.) Project Description: Land Reclamation/Shoreline Protection at Amadi Ama LGA, Rivers State
Name of Contractor: Messrs. Panama Construction Company Limited
Reviewed Project Cost (N): 1,434,400,664.69
Date: 18th May, 2011
Duration: 12 Months
iii.) Project Description: Land Reclamation/Shoreline Protection Project at Ogbobagbene, Burutu LGA, Delta State
Name of Contractor: Messrs. Snecou Group of Companies
Reviewed Project Cost (N): 2,431,040,276.95
Date: 18th May, 2011
Duration: 12 Months
TOTAL: N 5,813,743,373.92
3.) AWARD OF ENGINEERING CONTRACTS FOR THE CONSTRUCTION OF EMAKALAKALA-AKIPELAI ROAD AND BRIDGES IN BAYELSA STATE AND CONSULTANCY SERVICES FOR THE DESIGN OF SEAPORT DEVELOPMENT AT GELEGELE IN EDO STATE BY MINISTRY OF NIGER DELTA AFFAIRS
i.) Project Description: Contract for the Construction of Emakalakala-Akipelai Road and bridges in Bayelsa State
Name of Contractor: Messrs. Legacy By Merit Limited
Contract Sum (N): 3,313,465,196.33
Date: 18th May, 2011
Duration: 16 Months
ii.) Project Description: Contract for Consultancy Services for the Design of Seaport Development at Gelegele in Edo State
Name of Contractor: Messrs. Chris Epas Konsult Limited
Contract Sum (N): 224,989,864.00
Date: 18th May, 2011
Duration: 6 Months
TOTAL: N3,538,455,060.33
4.) Contract Item / Service: Augmentation of the Contract for the Dualization of the 99km East – West Road, Section III (Port Harcourt Eleme Junction – Eket) in Rivers/Akwa Ibom States: Contract No. 5882
Name of Company: Messrs. Reynolds Construction Company (Nigeria) Limited
Implementing Agency: Ministry of Niger Delta Affairs
Cost: Revised Contract Sum From N35,600,000,000.00 To N66,859,088,593.59
Date: 4th May, 2011
Duration: 31/12/12
5.) Contract Item / Service: Augmentation of the Contract for the Dualization of the 50km East – West Road, Section IV (Eket- Oron) in Akwa Ibom State: Contract No. 5883
Name of Company: Messrs. Gitto Construzioni Generali (Nigeria) Limited
Implementing Agency: Ministry of Niger Delta Affairs
Cost: Revised Contract Sum From N26,000,000,000.00 To N37,509,550,669.00
Date: 4th May, 2011
Duration: 11/06/ 2012
6.) Contract Item / Service: Augmentation of the Contract for the Construction of the Eket - Uyo – Itu 132kv Transmission Line
Name of Company: Messrs. Hoquado Nigeria Limited
Implementing Agency: Ministry of Power/ Niger Delta Power Holding Company Limited
Cost: Revised Contract Sum From USD41,782,510.04 Plus N2,158,080,051.60 USD63, 239,048.47 Plus N4,106,775,920.82
Date: 4th May, 2011
Duration: 12 Months for Transmission Line 18 Months for Substations
7.) Contract Item / Service: Augmentation of the Contract for the Construction of Alaoji-Owerri-Egbema- Omoku/Owerri-Nnewi-Onitsha 330kv DC Transmission Lines and Associated Substations
Name of Company: Messrs. Rockson Engineering Limited/Ak-Ay Elektric Dis Tikaret Kollektif Sirketi
Implementing Agency: Ministry of Power /Niger Delta Power Holding Company Limited
Cost: USD80,939,839.30 Plus N5,248,729,404.00 To USD140,353,686.30 Plus N17,004,620,318.00
Date: 4th May, 2011
Duration: December 2010 for Alaoji Sub station; September 2011 for Owerri and Omoku Substations; June 2012 for Transmission Lines
8.) Contract Item / Service: Augmentation of the Contract for the Construction of 1 x 30/40MVA 132/33KV Substation at Ikom and 132kv Line Bay Extensions at Abakaliki and Nkalagu Substations
Name of Company: Messrs. Renacs Engineering Company Limited
Implementing Agency: Ministry of Power/ Niger Delta Power Holding Company Limited
Cost: Revised Contract Sum From €3,868,582.28 Plus N338,040,562.16 €5,920,317.66 Plus N598,998,799.23 Payable at the prevailing exchange rate at the time of payment
Date: 4th May, 2011
Duration: 10 Months
9.) Contract Item / Service: Extension of Contract for the Design and Project Management Consultancy Services for NIPP Power Plants, Gas Pipelines, Transmission and Distribution Infrastructure
Name of Company: Messrs. Lahmeyer International /O.T. Otis Engineering
Implementing Agency: Ministry of Power/ Niger Delta Power Holding Company Limited
Cost: Revised Contract Sum From €17,905,290.00 Plus N944,617,665.00 To €25,123,133.86 Plus N3,134,714,755.00 Payable at the prevailing exchange rate at the time of payment
Date: 4th May, 2011
Duration: 24 Months
10.) Contract Item / Service: Augmentation of the Contract for the Construction of Makurdi – Jos 330kv Double circuit transmission line and associated 330/132kv substations at Makurdi and Jos
Name of Company: Messrs. North China Power Engineering (Beijing) Company Limited/ Chemo-Technics Limited
Implementing Agency: Ministry of Power/ Niger Delta Power Holding Company Limited
Cost: Revised Contract Sum From €58,880,529.76 Plus N4,844,230,902.00 To €65,760,407.74 Plus N6,703,934,056.58
Date: 4th May, 2011
Duration: July 2011
11.) Contract Item / Service: Extension of the Contract for the provision of Project Management Consultancy Service for the Construction of the Ihovbor and Sapele Power Plant projects
Name of Company: Messrs. John Brown GT/SGI Consulting
Implementing Agency: Ministry of Power
Cost: Revised Contract Sum From N226,103,000.00 To €455,262.50 Plus N284,942,201.00 Payable at the prevailing xchange rate at the time of payment
Date: 4th May, 2011
Duration: 31/03/2012
12.) Contract Item / Service: Award of Contract for the provision of onsite Technical Integrity Assessment Service on 18 Gas Turbines
Name of Company: Messrs. General Electric International Inc/ General Electric International Operations (Nigeria) Limited
Implementing Agency: Ministry of Power
Cost: USD4,919,471.76
Date: 4th May, 2011
Duration: 16 Months
13.) Contract Item / Service: for the provision of Project Management Consultancy Service for the Construction of the 676MW Olorunsogo Phase II Power plant
Name of Company: Messrs. Scott Wilson/Oska –Jo & Partners
Implementing Agency: Ministry of Power
Cost: Revised Contract Sum From £605,479.30 Plus N262,466,713.52 To £612,019.30 Plus N432,033,913.52
Date: 4th May, 2011
TOTAL: N17,141,746.85
14.) VARIATION OF CONTRACT FOR THE CONSTRUCTION OF 451MW SAPELE POWER PLANT PROJECT UNDER THE NIGER DELTA POWER HOLDING COMPANY BY MINISTRY OF POWER
i.) Project Description: Revision of the Project Cost on Contract for the Construction of Sapele Power Plant Project
Name of Contractor: Messrs. Marubeni Corporation/Marubeni Engineering (WA) Limited
Contract Sum (N): USD1,470,000.00 to cover the cost of inland waterways transportation of heavy-lift generation equipment from Warri port to site
Date: 18th May, 2011
ii.) Project Description: Revision of the Project Cost on Contract for the Construction of Sapele Power Plant Project
Name of Contractor: Messrs. Marubeni Corporation/Marubeni Engineering (WA) Limited
Contract Sum (N): USD3,181,085.10 to cover the cost of storage of plant and machinery
Date: 18th May, 2011
iii.) Project Description: Revision of the Project Cost on Contract for the Construction of Sapele Power Plant Project
Name of Contractor: Messrs. Marubeni Corporation/Marubeni Engineering (WA) Limited
Contract Sum (N): USD4,661,400.00
Date: 18th May, 2011
iv.) Project Description: Revision of the Project Cost on Contract for the construction of Sapele Power plant project
Name of Contractor: Messrs. Marubeni Corporation/Marubeni Engineering (WA) Limited
Contract Sum (N): USD7,829,261.75
Date: 18th May, 2011
TOTAL: N17,141,746.85
15.) VARIATION OF CONTRACTS FOR THE CONSTRUCTION OF IHOVBOR AND CALABAR POWER PLANTS PROJECTS UNDER THE NIGER DELTA POWER HOLDING COMPANY TO COVER STORAGE AND INSURANCE COSTS ON OEM GENERATION EQUIPMENT BY MINISTRY OF POWER
i.) Project Description: Revision of the Project Cost on the Contract for the Construction of the Ihovbor Power Plant
Name of Contractor: Messrs. Marubeni Engineering (West Africa) Ltd./ Marubeni Corporation
Contract Sum (N): Revised Contract Sum From USD117,859,171.41 To USD121,873,086.82 to cover the cost storage and insurance on the OEM equipment supplied by General Electric Payable at the prevailing exchange rate at the time of payment
Date: 18th May, 2011
ii.) Project Description: Revision of the Project Cost on the Contract for the Construction of the Calabar Power Plant
Name of Contractor: Messrs. Marubeni Engineering (West Africa) Ltd./ Marubeni Corporation
Contract Sum (N): Revised Contract Sum From USD150,714,461.00 Plus N211,874,213.25 To USD157,245,623.01 Plus N211,874,213.25 to cover the cost storage and insurance on the OEM equipment supplied by General Electric Payable at the prevailing exchange rate at the time of payment
Date: 18th May, 2011