FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS FOR AUGUST 29, 2012
1) Contract Item/ Service: Approval of the Revised Estimated Total Cost for the Gurara Water Transfer Project Lot B, Construction of Azara-Jere Irrigation Scheme
Name of Company: Messrs SCC (Nigeria) Limited
Implementing Agency: Federal Ministry of Water Resources
Cost: Revised Estimated Total Cost of N26,447,872,659.49
Date: 29/08/12
Duration: Extended Completion period of 36 Months
2) Contract Item/ Service: Approval of the Revised Estimated Total Cost for the Construction of Ilesha Dam and Water Supply Scheme (Phase I)
Name of Company: Messrs Reynolds Construction Company (Nigeria)Limited
Implementing Agency: Federal Ministry of Water Resources
Cost: Revised Estimated Total Cost of N3,699,950,856.91
Date: 29/08/12
Duration: 24 Months