Posted by Charles on Wed 17th Oct, 2012 - nigeriantenders.com
FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS FOR DECEMBER 07, 2011
1.) Contract Item/Service: Award of contract for the construction OF Police Service Commission Corporate Head Office Building, Abuja
Name of Company: Messrs. Vita Construction Nigeria Ltd
Implementing Agency: Presidency/Police Service Commission
Cost: N3,486,867,519.53
Date: 7th December, 2012
Duration: 15 Months
2.) Contract Item/Service: Award of contract for Procurement, Installation and Commissioning of ILS/DME in 5 Airports and DVOR/DME in 5 Airports
Name of Company: Messrs. Salbodi Group Ltd/Indra Sistemas S.A
Implementing Agency: Ministry of Aviation
Cost: N1,590,361,027.20
Date: 7th December, 2012
Duration: 10 Months
3.) Contract Item/Service: Direct/repeat Procurement of additional 696No. of SCA 120IN Heat Proximity Clothing form the Original Equipment Manufacturers
Name of Company: Messrs. Sancheong Products of South Korea Through Messrs. Plastisol BV of the Netherlands (Accredited Representatives in Nigeria)
Implementing Agency: Ministry of Aviation
Cost: N299,708,736.00
Date: 7th December, 2012
Duration: 4 Months
4.) Contract Item/Service: Award of contracts for the Operation, Maintenance and Training of Staff for Wupa Basin Sewage Treatment Plant
Name of Company: Messrs. SCC (Nigeria) Limited
Implementing Agency: Federal Capital Territory
Cost: N1,586,451,516.76
Date: 7th December, 2012
Duration: 2 Years (from 16th April 2011 to 15th April 2013)
5.) Contract Item/Service: Award of contract for consultancy services for stages 1 and 2 in respect of the construction of new Federal Inland Revenue Service (FIRS) Headquarters building in Abuja
Name of Company: Messrs. ATO Architects as consultant architects and their team of other consultants: Structural Engineers, Messrs. IAA Associates Ltd; Mechanical Engineers, Messrs. Molecular Consultants and Associates; Electrical Engineers, Messrs. Molecular Consultants and Associates; and Quantity Surveyors, Messrs. Sea Surveyors Ltd
Implementing Agency: Ministry of Finance/ FIRS
Cost: N733,427,476.78
Date: 7th December, 2012
Duration:6 Months
6.) Contract Item/Service: Procurement of contraceptive by the United Nations Fund for Population Activities (UNFPA) for the Federal Ministry of Health
Name of Company: United Nations Fund for Population Activities (UNFPA)
Implementing Agency: Ministry of Health
Cost: USD3,000,000.00 Federal Government counterpart funding
Date: 7th December, 2012
7.) Contract Item/Service: Award of contract for the Construction of the National Information Technology Center by Galaxy Backbone Plc
Name of Company: Messrs. Sageto (Nig) Ltd
Implementing Agency: Ministry of Communications Technology
Cost: N7,274,638,250.51
Date: 7th December, 2012
Duration:104 weeks
8.) Contract Item/Service: Award of contract for additional works to address the gully erosion at Chainages 9+700 and 11+400 be executed on the contract for the Rehabilitation of Onitsha – Enugu Dual Carriageway Section II; Anambra State Border – Enugu Road
Name of Company: Messrs. CCC (Nigeria) Limited
Implementing Agency: Ministry of Works
Cost: N710,135,133.75
Date: 7th December, 2012
Duration:24 Months
9.) Contract Item/Service: Augmentation of contract for the Rehabilitation of Obiozora-Uburu-Mpu-Ishiagu-Portharcourt Expressway Road
Name of Company: Messrs. Setraco (Nigeria)Limited
Implementing Agency: Ministry of Works
Cost: N8,367,343,094.25
Date: 7th December, 2012
Duration: 12 Months
10.) Contract Item/Service: Award of contract for the completion of Nkari Dam Project in Akwa Ibom State
Name of Company: Messrs. A.G Vision
Implementing Agency: Ministry of Water Resources
Cost: N2,911,284,239.73
Date: 7th December, 2012
Duration: 24 Months
11.) Contract Item/Service: Augmentation of contract for the construction of Ogbese Multi-purpose Dam Project in Ekiti State
Name of Company: Messrs. Foundation Solid (Nigeria) Limited
Implementing Agency: Ministry of Water Resources
N7,802,436,568.66
Date: 7th December, 2012
Duration: 36 Months
12.) Contract Item/Service: Award of contract for the repairs to the Goronyo Dam emergency spillway
Name of Company: Messrs. Gilmor Engineering (Nig) Limited
Implementing Agency: Ministry of Water Resources
Cost: N3,882,146,985.99
Date: 7th December, 2012
Duration: 8 Months
13.) Contract Item/Service:Award of contract for the Construction of Ogwashi-Uku Multipurpose Earth Dam Phase II
Name of Company: Messrs. Nelson Benjamin Limited
Implementing Agency: Ministry of Water Resources
Cost: N3,615,323,794.01
Date: 7th December, 2012
Duration: 24 Months
14.) Contract Item/Service: Augmentation of the contract sum for the Rehabilitation of Lagos Harbour Moles
Name of Company: Messrs. China Civil Engineering and Construction Corporation (CCECC) Ltd
Implementing Agency: Ministry of Transport/Nigeria Ports Authority
Cost: Revised Estimated Total Cost N20,035,710,566.72
Date: 7th December, 2012
Duration: 21 Months
15.) AWARD OF CONTRACT FOR THE CONSTRUCTION OF 6No. NEW FEDERAL GOVERNMENT SECRETARIATS IN EACH GEO-POLITICAL ZONE OF THE FEDERATION
i. Project Title/Location: Federal Government Secretariat, Awka, Anambra State
Contractors: Messrs. Cosco Investment (Nig) Ltd
Implementing Agency: Ministry of Lands, Housing and Urban Development
Project Cost: N2,561,268,866.56
Date: 7th December, 2012
Completion Period: 100 weeks
ii. Project Title/Location: Federal Government Secretariat, Yenagoa, Bayelsa State
Contractors: Messrs. Trenure (Nig) Ltd
Implementing Agency: Ministry of Lands, Housing and Urban Development
Project Cost: N2,561,268,866.56
Date: 7th December, 2012
Completion Period: 100 weeks
N2,563,476,419.85
iii. Project Title/Location: Federal Government Secretariat, Gombe, Gombe State
Contractors: Messrs. Vic Phranc (Nigeria) limited
Implementing Agency: Ministry of Lands, Housing and Urban Development
Project Cost: N2,561,268,866.56
Date: 7th December, 2012
Completion Period: 100 weeks
N2,293,261,561.05
iv. Project Title/Location: Federal Government Secretariat, Lafia, Nassarawa State
Contractors: Messrs. Faplins (Nig) Ltd
Implementing Agency: Ministry of Lands, Housing and Urban Development
Project Cost: N2,229,968,101.20
Date: 7th December, 2012
Completion Period: 100 weeks
v. Project Title/Location: Federal Government Secretariat, Osogbo, Osun State
Messrs. Golden Construction Company Limited
Implementing Agency: Ministry of Lands, Housing and Urban Development
Project Cost: N2,548,444,283.80
Date: 7th December, 2012
Completion Period: 100 weeks
vi. Project Title/Location: Federal Government Secretariat, Gusau, Zamfara State
Contractors: Messrs. Sageto Ltd
Implementing Agency: Ministry of Lands, Housing and Urban Development
Project Cost: N2,528,673,102.10
Date: 7th December, 2012
Completion Period: 100 weeks
15.) AWARD OF CONTRACTS FOR DIRECT PROCUREMENT OF ANTI-RETROVIRAL (ARV) DRUGS AND OTHER COMMODITIES
i. Project Description: Supply of 50,576 packs of Lamivudine/Zidovudine/Nevirapine ARV MDG Branded Drug
Contractors: Messrs. Emcure Nigeria Limited
Implementing Agency: Federal Ministry of Health
Contract Sum: N124,500,000.00
Date: 7th December, 2012
Completion Period: 2 weeks
ii. Project Description: Supply of 50,576 packs of Lamivudine/Zidovudine/Nevirapine ARV MDG Branded Drug
Contractors: Messrs. Strides Vital Nigeria Limited
Implementing Agency: Federal Ministry of Health
Contract Sum: N126,990,000.00
Date: 7th December, 2012
Completion Period: 2 weeks
iii.Project Description: Supply of 50,576 packs of Lamivudine/Zidovudine/Nevirapine ARV MDG Branded Drug
Contractors: Messrs. Ranbaxy Nigeria Limited
Implementing Agency: Federal Ministry of Health
Contract Sum: N112,050,000.00
Date: 7th December, 2012
Completion Period: 2 weeks
iv. Project Description: Supply of 50,576 packs of Lamivudine/Zidovudine/Nevirapine ARV MDG Branded Drug
Contractors: Messrs. Evans Medical Plc
Implementing Agency: Federal Ministry of Health
Contract Sum: N136,651,200.00
Date: 7th December, 2012
Completion Period: 2 weeks
v. Project Description: Supply of 50,576 packs of Lamivudine/Zidovudine/Nevirapine ARV MDG Branded Drug
Contractors: Messrs. May & Baker Nigeria Plc
Implementing Agency: Federal Ministry of Health
Contract Sum: N129,480,000.00
Date: 7th December, 2012
Completion Period: 2 weeks
vi. Project Description: Supply of 55,000 tablets of Cotrimoxazole tablets and 108,108 100ml suspension of co-trimoxazole
Contractors: Messrs. Clarion Medical limited
Implementing Agency: Federal Ministry of Health
Contract Sum: N145,860,000.00
Date: 7th December, 2012
Completion Period: 2 weeks
vii. Project Description: Supply of 428,000 tests Double Check Gold
Contractors: Messrs. Biotec Laboratory Products
Implementing Agency: Federal Ministry of Health
Contract Sum: N194,033,880.00
Date: 7th December, 2012
Completion Period: 2 weeks
viii.Project Description: Supply of 428,000 tests of Determine Test kits
Contractors: Messrs. Acouns Nigeria Limited
Implementing Agency: Federal Ministry of Health
Contract Sum: N194,033,880.00
Date: 7th December, 2012
Completion Period: 2 weeks
ix.Project Description: Supply of 428,000 Stat Pak Test Kits
Contractors: Messrs. Chembio Diagnostics Limited
Implementing Agency: Federal Ministry of Health
Contract Sum: N194,033,880.00
Date: 7th December, 2012
Completion Period: 2 weeks
TOTAL: N1,357,632,840.00
15.) AWARD OF CONTRACTS FOR THE CONSTRUCTION OF TRANSMISSION LINES AND SUBSTATIONS FOR THE TRANSMISSION COMPANY OF NIGERIA(TCN)
i. Project Description: Lot 2011 – 1 Engineering, design, manufacture, Supply, Construction and Commissioning of the 235km 2nd Kaduna-Kano 330kv Double Circuit Transmission Line
Contractors: Messrs. National Power Construction Corporation
Implementing Agency: Ministry of Power/Transmission Company of Nigeria (TCN)
Contract Sum: USD42,968,950.21 Payable at prevailing rate at the time of exchange Plus N4,154,133,631.19
Date: 7th December, 2012
Completion Period: 24 months
ii. Project Description: Lot 2011 – 2 Engineering, design, manufacture, Procurement, Supply, Construction and Commissioning of the 150km Delta-Portharcourt 330kv Double Circuit Transmission Line
Contractors: Messrs. Icomm Tele Ltd/PPP International Ltd
Implementing Agency: Ministry of Power/Transmission Company of Nigeria (TCN)
Contract Sum: USD27,079,493.25 Plus N3,627,601,391.33
Date: 7th December, 2012
Completion Period: 24 months
iii. Project Description: Lot 2011-3 Abakaliki-Amasiri 132kv Double Circuit Transmission Line
Contractors: Messrs. Flour Engineering/Eurafric Energy Ltd
Implementing Agency: Ministry of Power/Transmission Company of Nigeria (TCN)
Contract Sum: USD6,044,617.26 Plus N898,080,164.52
Date: 7th December, 2012
Completion Period: 24 months
iv. Project Description: Lot 2011-4 Keffi-Kwoi-Kachia 132kv Double Circuit Transmission Line
Contractors: Messrs. Aster Infrastructures
Implementing Agency: Ministry of Power/Transmission Company of Nigeria (TCN)
Contract Sum: USD9,495,089.71 Plus N1,587,493,882.99
Date: 7th December, 2012
Completion Period: 24 months
v. Project Description: Lot 2011-5 Ugwuaji-Nnenwe 132kv Double Circuit Transmission Line
Contractors: Messrs. Ashtavinayaka Energy Infra Pvt Ltd/Bran Engineering Ltd
Implementing Agency: Ministry of Power/Transmission Company of Nigeria (TCN)
Contract Sum: USD3,732,770.65 Plus N511,793,146.63
Date: 7th December, 2012
Completion Period: 24 months
vi. Project Description: Lot 2011-6 132kv Double Circuit Transmission Line Nnewi MBO
Contractors: Messrs. Dorman Long Engineering/Genesis/Power Projects Ltd Nnenwe-Mpu
Implementing Agency: Ministry of Power/Transmission Company of Nigeria (TCN)
Contract Sum: USD2,858,534.87 Plus N643,790,391.31
Date: 7th December, 2012
Completion Period: 24 months
vii. Project Description: Lot 2011 – 7 Engineering, design, manufacture, Supply, Construction and Commissioning of the 50km Omuaran -Egbe 330kv Double Circuit Transmission Line
Contractors: Messrs. Aravali Infra Power Limited/Alicon Ventures Nig. Ltd
Implementing Agency: Ministry of Power/Transmission Company of Nigeria (TCN)
Contract Sum: USD3,088,924.41 Plus N621,321,904.69
Date: 7th December, 2012
Completion Period: 24 months
viii. Project Description: Lot 2011 – 8 Engineering, design, manufacture, Procurement, Supply, Construction and Commissioning of the 90km Obajana-Okeagbe 330kv Double Circuit Transmission Line
Contractors: Messrs. Everest Infra Energy Ltd/Dyehnum ventures Ltd
Implementing Agency: Ministry of Power/Transmission Company of Nigeria (TCN)
Contract Sum: USD7,743,804.84 Plus N803,692,934.38
Date: 7th December, 2012
Completion Period: 24 months
ix. Project Description: Lot 2011 – 9 Engineering, design, manufacture, Supply, Construction and Commissioning of the 180km Yola-Song-Little Gombi-Mubi-Gulak 330kv Double Circuit Transmission Line
Contractors: Messrs. Skipper Electricals/Summit Energy
Implementing Agency: Ministry of Power/Transmission Company of Nigeria (TCN)
Contract Sum: USD25,545,146.96 Plus N3,471,734,877.83
Date: 7th December, 2012
Completion Period: 24 months
ix. Project Description: Lot 2011 – 10 Design, manufacture, Supply,and Commissioning of 2x330kv Lines Bay Extension in each of Kaduna (Mando) and Kano( Kumbotso) 330/132kv substation
Contractors: Messrs. Exernegia Power Africa Bigen
Implementing Agency: Ministry of Power/Transmission Company of Nigeria (TCN)
Contract Sum: USD4,212,379.53 Plus N500,823,961.92
Date: 7th December, 2012
Completion Period: 24 months
xi. Project Description: Lot 2011-11 2x330kv Line bays extension in each of Delta (Ughelli) and portharcourt 330/132kv substation
Contractors: Messrs. MBH Power Ltd
Implementing Agency: Ministry of Power/Transmission Company of Nigeria (TCN)
Contract Sum: USD4,401,074.24 Plus N551,133,551.17
Date: 7th December, 2012
Completion Period: 24 months
xii. Project Description: Lot 2011 – 13 Design, manufacture, Supply, Construction and Commissioning of 2x60MVA, 330/132kv substation at Kachia
Contractors: Messrs. Esterbag Engineering Limited
Implementing Agency: Ministry of Power/Transmission Company of Nigeria (TCN)
Contract Sum: USD6,031,516.62 Plus N437,340,330.79
Date: 7th December, 2012
Completion Period: 24 months
xiii. Project Description: Lot 2011 – 16 Design, manufacture, Supply, Commissioning of 2x60 MVA, 132/33kv substation at Okeagbe and 2x132kv line bays extension at Obajana
Contractors: Messrs. Power Contral & Appliances
Implementing Agency: Ministry of Power/Transmission Company of Nigeria (TCN)
Contract Sum: USD5,612,652.66 Plus N687,987,881.45
Date: 7th December, 2012
Completion Period: 24 months
xiv. Project Description: Lot 2011 – 17 Design, manufacture, Supply, and Commissioning of 2x60MVA, 132/33kv substation at Song and 2x132kv Lines Bay Extension at Yola
Contractors: Messrs. Qingdao Wuxio Grwa Company ltd/Ahmin Technology and Power System
Implementing Agency: Ministry of Power/Transmission Company of Nigeria (TCN)
Contract Sum: USD6,506,881.47 Plus N676,045,227.30
Date: 7th December, 2012
Completion Period: 24 months
xv. xiii. Project Description: Lot 2011 – 18 Design, manufacture, Supply, and Commissioning of 2x60MVA, 132/33kv substation at Little Gombi
Contractors: Messrs. Shandong Taikai
Implementing Agency: Ministry of Power/Transmission Company of Nigeria (TCN)
Contract Sum: USD4,852,409.00 Plus N711,474,893.72
Date: 7th December, 2012
Completion Period: 24 months
xvi. Project Description: Lot 2011 – 19 Design, manufacture, Supply, and Commissioning of 2x60MVA, 132/33kv substation at Mubi
Contractors: Messrs. Hyundi/Richfield
Implementing Agency: Ministry of Power/Transmission Company of Nigeria (TCN)
Contract Sum: USD5,534,586.81 Plus N574,978,088.57
Date: 7th December, 2012
Completion Period: 24 months
xvii. Project Description: Lot 2011-20 2X60MVA, 132/33kv substation at Gulak
Contractors: Concepts Engineering Pvt India/Chanref (Nig) Ltd
Implementing Agency: Ministry of Power/Transmission Company of Nigeria (TCN)
Contract Sum: USD5,333,749.93 Plus N1,044,144,867.47
Date: 7th December, 2012
Completion Period: 24 months